The Philippine Ports Authority (PPA) board recently approved the detailed development design for North Port submitted by operator Manila North Harbour Port, Inc (MNHPI).

“All approved designs only cover Terminal 1 while the other designs are still pending,” Manila and North Luzon engineer Constante Fariñas said.

PPA approved an extension of completion date for the port’s Terminal 1 passenger terminal building to November 2013, eight months later than the original date of April 2013.

Despite the longer completion date approved by PPA, MNHPI committed to finish the project by next year, Fariñas said.

PPA also approved collapsing the development of two passenger terminal buildings into only one.

A joint venture between Harbour Centre Port Terminals, Inc and San Miguel Corp, MNHPI committed to sink in P14.5 billion to develop a container terminal, general cargo terminal, and passenger terminal at North Port.

Phase I of the project will be implemented over a period of six  years. The first year of the contract requires completion of a crane rail for two load-on load-off berths and pavement/concreting of container yards. After completion of the crane rail, the operator will procure two shore cranes and support equipment.

So far, the joint venture has invested P1 billion, of which P650 million was provided by Harbour Centre and the rest by San Miguel for the purchase of equipment.

Another P1 billion was infused partly for the interim passenger terminal and container terminal. The port has a capacity of 1.2 million TEUs to 1.5 million TEUs.

This year, MNHPI expects to handle 780,000 twenty-foot equivalent units (TEUs), up from last year’s 630,000 TEUs. The port has a capacity of 1.5 million TEUs.

 

Photo by Will Scullin 

You May Also Like
PortCalls to conduct Cebu training for logistics stakeholders in Sept

PortCalls to conduct Cebu seminars for logistics stakeholders in Sept

PortCalls is conducting eight seminars for logistics stakeholders in Cebu City next…

PPA new policy on standardized tariffs, fees not retroactive

The Philippine Ports Authority’s new policy on the computation of port tariffs…

PH local trade hits 16M tons in Q1 2025

The Philippines’ domestic trade reached 16.05 million tons amounting to P1.230 trillion…

P14.82B San Ramon Newport contract likely to be signed in May 2026

The contract for the proposed P14.82-billion San Ramon Newport Project is aimed…