Asia Pacific port operations improve in Nov, including Manila: DHL
Image from DHL
  • Port operations across Asia Pacific are generally normal, except in Manila and at Shanghai WQG and Ningbo – although delays have decreased to 2-5 days from 5+ days
  • In North and South America, operations remain mixed
  • In North Europe, prevailing congestion and schedule reliability challenges are expected to persist until the end of the year; South European ports are performing better and expected to remain stable.
  • Tensions in the Middle East continue to significantly affect the Jebel Ali and Dammam ports
  • Durban in South Africa faces particularly severe berth waiting times of 6–15 days

Port operations across Asia Pacific are generally normal, with good equipment availability and delays within the 1-2 days range considered as minor, except in Manila and at the world’s two busiest ports, Shanghai WQG and Ningbo in China, at 2-5 days, according to DHL.

In its  Ocean Freight Port Situation Update for November 2026, DHL said the region is considered in a “stable” status although some congestion and elevated terminal utilization are causing moderate disruption in selected areas.

The port operations in Manila, Shanghai WQG and Ningbo have already improved from delays of more than 5 days in recent months.

READ: Congestion persists at two busiest China ports, Manila – DHL report

In both Shanghai and Ningbo, equipment is not a problem nor are there hinterland issues. Meanwhile, operations at Shanghai Yangshan – which was also at over 5 days in September –has improved with no more delays nor other issues seen.

In south-east Asia, only Manila is seeing 2-5 days delay as well as berth congestion. All its neighbors – including Singapore, Vietnam and Malaysia – as well as ports in India are operating within normal levels.

North, South America

In North and South America, operations remain mixed, with several areas experiencing moderate to significant delays, congestion, equipment constraints and inland transport disruptions, while other locations continue to operate relatively smoothly, DHL said.

In Los Angeles, the busiest port in the United States, delays are more than five days and there are some road issues.

Europe

In North Europe, prevailing congestion and schedule reliability challenges are expected to persist until the end of the year, while inland transport constraints continue to limit network recovery.

On the other hand, South European ports are performing with lower congestion levels and stronger schedule reliability and are expected to remain stable.

Middle East & Africa

Tensions in the Middle East continue to significantly affect the Jebel Ali and Dammam with delays of more than five days and major road constraints linked to the reported closure of the Hormuz Strait.

Durban in South Africa, meanwhile, faces particularly severe berth waiting times of 6–15 days.

Other areas in the Middle East and Africa are generally operating smoothly.

READ: Asia Pacific air and sea freight rates, capacity are diverging–DHL