  • Construction of Mindanao Container Terminal’s 300-meter berth extension is progressing, with the first 120 meters targeted for completion by the end of the first quarter of 2027
  • The berth expansion, recent delivery of four new hybrid rubber-tired gantry cranes, and the order of three post-Panamax quay cranes are part of MCT’s expansion program to ramp up its capacity to accommodate rising cargo demand and additional shipping services
  • The program also includes expanded reefer facilities, additional container storage capacity, and construction of a new electrical substation

Construction of Mindanao Container Terminal’s (MCT) 300-meter berth extension is progressing, with the first 120 meters targeted for completion by the end of the first quarter of 2027.

The berth expansion, as well as the recent delivery of four new hybrid rubber-tired gantry cranes, are part of MCT’s expansion program to ramp up its capacity to accommodate rising cargo demand and additional shipping services.

The program also includes the order of three post-Panamax quay cranes, expanded reefer facilities, and additional container storage capacity.

“We formalized the project in late 2024 and established a clear timetable. I’m pleased to say that everything remains on schedule,” MCT chief executive officer Aurelio Garcia said in a statement.

READ: ICTSI’s Mindanao terminal to add 180 reefer plugs by 2027

The RTGs arrived roughly three months ahead of schedule, marking an important step in the terminal’s expansion and highlights the progress being made across MCT’s expansion program, Garcia noted.

“While we’ve seen construction progress over the past several months, seeing the first RTG arrive and be discharged was a significant moment for the project. It reflects the progress being made across the terminal and the work that continues behind the scenes,” Garcia said.

Following the completion of the first 120 meters of the berth extension in 2027, the first of three new post-Panamax quay cranes is expected to arrive shortly afterward and will become operational following commissioning.

Once completed, the initial phase will increase MCT’s operational berth length to 420 meters, providing additional capacity for vessel calls and shipping services.

The current phase forms part of MCT’s long-term expansion program, which is scheduled for completion in the first quarter of 2028. By then, MCT is expected to complete the full 300-meter berth extension and commission all three quay cranes.

MCT operator Mindanao International Container Terminal Services, Inc. (MICTSI) in 2024 announced it will invest more than US$100 million in infrastructure upgrades, including the berth extension and the acquisition of new equipment to support projected cargo volume growth. MICTSI in 2024 secured an additional 25 years to manage and operate MCT.

MICTSI is part of the International Container Terminal Services, Inc. group.

Other additional infrastructure

The expansion program also includes additional infrastructure to support MCT’s growing operations. MCT is expanding its reefer facilities to accommodate increasing volumes of refrigerated import and export cargo, while work is underway to expand the empty container depot and increase container storage capacity.

Supporting infrastructure projects include the construction of a new electrical substation that will provide the power required for additional equipment and future operational needs.

Located within the Phividec Industrial Estate in Tagaloan, Misamis Oriental, MCT serves as Northern Mindanao’s primary international container gateway. The terminal supports the movement of import and export cargoes and helps connect businesses across the region with domestic and international markets.

“With additional berth capacity becoming available next year, we expect to be in a stronger position to accommodate more vessel calls and support additional shipping services,” Garcia said.

“We look forward to completing the program on schedule and continuing to build on MCT’s role in supporting trade and industry in Mindanao,” he added.